Data centre developers carry 90% of the liability when builds run late
3 min readLONDON, 17 November 2026 – Only around 10% of late-delivery fees are typically recoverable from the contractor, leaving a shortfall of USD74 million to USD80 million on a 60MW build that is four months late.
When a data centre runs late, the developer carries about 90% of the liability, according to STL Partners’ When days cost millions: Getting ahead of data centre delay risk. Only around 10% of late-delivery fees are typically recoverable from the contractor: on a 60MW build, a four-month delay implies a shortfall of USD74 million to USD80 million. The report, produced with the support of Foresight Works and with input from Howden, finds that 93% of the 99 data centre finance, risk and development leaders surveyed carry tenant liabilities exceeding what they can recover from contractors.
“Data centre developers are caught between two opposing forces, with delays leaving them exposed to tenant break clauses and SLA penalties, but without the ability to recover associated losses from general contractors on whom they are dependent to complete future developments. While, to date, tenants have rarely exercised break clauses, as the supply-demand balance for capacity equalizes, it is imperative developers do not rely on the status quo to protect them against the financial impact of delays, and invest in solutions and capabilities which minimise the risk of such delays” – Joe Hurman, Principal Consultant and Data Centre Lead at STL Partners.
The gap is not an occasional problem. In the survey, 46% of respondents say their exposure to tenants exceeds what they can recover from contractors on half or more of their projects. STL Partners finds there is no industry standard for managing the difference: 34% say the owner simply retains it, and only 13% say it is partly insured or transferred.
For now, little of the liability is settled in cash. Developers waive contractor compensation to keep scarce contractors for the next phases and projects, and tenants tend to trade credits for lower rent on later leases, so the developer still pays, later and out of sight.
Insurance closes only part of the gap. Only 39% of respondents bought delay-in-start-up cover on their last project, and four in five respondents (79%) say contracts and insurance together cover less than half of their delay exposure.
STL Partners makes five key recommendations to CFOs responsible for financial management of data centre developments:
1. Make delay a core sensitivity in the project finance model
2. Draft contractor and supplier contracts to maximise recovery, and to make it collectable
3. Evaluate the insurance market actively and engage specialist brokers early to choose the right model for each project
4. Invest to avoid delay rather than delivering at minimum viable cost
5. Keep every party working from the same facts, so that individual delays do not escalate
The report, When days cost millions: Getting ahead of data centre delay risk, is free to download. It was produced with the support of Foresight Works, with input from Howden.